West Midlands Pre-Heater Replacement 2012

New modular condensing boilers and heat exchangers were installed along with all associated mechanical and civils works as necessary to complete the upgrade.

The scope of works included the following;

  • Site setup and provision of welfare arrangements
  • Removal and disposal of existing modular boilers, including disposal of glycol.
  • Dismantling removal and disposal of all existing redundant plant and pipe work
  • Support during installation and commissioning of new boiler house
  • Stringing
  • Welding
  • E&I Infrastructure
  • Welding & Fabrication
  • NDT
  • Testing and drying of pipework
  • Insulation of above ground pipework and heat exchangers
  • Civil works are required